Project description
Today we present the rehabilitation of the football stadium located in the town of Torredembarra (Tarragona)
The steps for rehabilitation have been as follows:
- Cleaning the support with pressurized water.
- Reconstruction of damage to concrete.
- Application of 2 coats of epoxy primer with aggregate dusting to improve the anchorage of the membrane.
- Waterproofing by applying a Impermax 2K hot polyurethane membrane with TEE nº10 / 0296 for 25 years with a 2kg / m2 envelope.
- Non-slip aliphatic protection finish applied in 2 coats with Kodpton Chemical SL Colodur pigmented Topcoat in a 350gr / m2 envelope.